Quick Project Turnaround | South Yarra

Location: South Yarra Challenge: Short duration turnaround with a team of 12 men completed 500m2 multiple coats in a little over 14 hours. Outcome: Delivered a Hychem methylmethacrylate or PUMA system to waterproof bridge decks prior to rail & asphalt

Emergency Repairs

Remcon Group attending to an urgent response. Day or night. Our team works 24/7 to get the job done. Issue: Emergency Repairs to Expansion Joints Solution: We attended the site quickly to remove, repair and re-instate this plate in a single overnight shift.

Robotic Demolition

A return client contacted us informing us that an escalator didn’t fit through to the desired installation location. If the escalator would need to be reordered it would delay the project schedule by 6 months. Remcon was able to provide a timely solution and make it fit. Solution: By removing 400mm thick, 20m² of concrete […]